Projet

Repatriation of the M’Ghira Industrial Zone 5 -Ben Arous

  • Pickling topsoil:
  • Pickling topsoil to an average thickness of 20 cm in all types of terrain including:
    • Picking and surveying necessary,
    • The establishment of a file of execution including calculation of cubatures
    • The clearance of anarchic embankments existing whatever their natures outside the site
    • The weeding and felling of trees and shrubs, whatever their size, including the extraction of roots, whatever their depth
    • The coordination with the concessionaires to locate the existing networks and the realization of the necessary surveys for their recognitions as well as their backups in good condition,
    • The release of all stripping products to the public landfill including loading, transport, unloading.
    • The temporary drainage works of the platform, And all subjections …
  • Supply and execution of embankments (IP <12, ES> 20):
  • The supply and execution of backfill (IP <12) from a deposit requested by the Contractor and approved by the Administration, including:
    • Adjustment and compaction of the embankment platform,
    • The supply of selected materials whose characteristics meet the specifications of the CCTP including IP <12 and Equivalent de Sable> 20,
    • Spreading materials in successive layers not exceeding 25 cm compatible with the nature of the materials and the compaction means,
    • Watering or aeration to obtain the required water content,
      95% compaction of the OPM according to the requirements of the CCTP,
    • Acceptance testing of materials and work control And all subjections
  • Reprofiling and cleaning of the canal crossing the area
  • The execution of the cuttings necessary for reprofiling and the cleaning of the canal crossing the zone including;
    • The execution of the work of weeding and cleaning the right of way of water courses whatever the nature of the existing waste and whatever the nature and age of the plants including access to the work, use of material means water pumping, removal of vases …
    • Demolition of obstacles encountered and existing structures whatever their size and nature, including the demolition of their foundations and the evacuation of products to the dump,
    • The execution of the necessary clearing works on all kinds of land to create the shape of the wadi with the creation of a suitable longitudinal slope including the loading, the transport, the unloading in the dump or the storage in a place designated by the Project Manager,
    • The clearance of the cuttings resulting from the operation of the cleaning and profiling outside the site,
    • The protection of the platforms, the adjustment, the watering and the compaction of the bottom and the slopes,
    • Supply and execution, if necessary, of embankments coming from the selected materials, including access to the structure, replenishment, watering, compacting by layer of 20cm up to 95% of the OPM.
    • Cleaning and cleaning of the existing canal.
  • Execution of an earthen ditch b =1; h =2; m =1/1:
  • The execution of the cuttings necessary for the creation of a dirt ditch along the existing tracks in accordance with the layout of the plan and the profile including:
    • The execution of the work of weeding and cleaning the right of way of water courses whatever the nature of the existing waste and whatever the nature and age of the plants including access to the work, use of material means pumping of water, removal of vases and clearing of cuttings from this operation off site,
    • Demolition of obstacles encountered and existing structures whatever their size and nature, including the demolition of their foundations and the evacuation of products to the dump,
    • The execution of the necessary clearing works on all types of land to create the shape of the ditch in accordance with the plans with the creation of a suitable longitudinal slope towards the channel crossing the zone including the loading, the transport, the unloading in the public dump or storage in a place designated by the Project Manager,
    • Temporary diversion work of the platform drainage,
    • The protection of the platforms, the adjustment, the watering and the compaction of the bottom and the slopes,
    • Supply and execution, if necessary, of embankments coming from the selected materials, including access to the structure, replenishment, watering, compacting by layer of 20cm up to 95% of the OPM.